Deadline for public comment is Nov. 27

As the deadline approaches for public comment on a proposed transmission line that would cut through the forested hill opposite Garrison's Landing, the U.S. Army plans to shorten its environmental review under recently adopted federal regulations.

The plan to construct transmission lines and two substations to increase power to West Point has drawn criticism from environmental groups, historic preservation groups and residents because it will alter the viewsheds of historic districts, including Garrison's Landing, Harriman State Park and the Thayer Hotel and Buffalo Soldier Field at the military academy.



Jeffrey Anzevino of Scenic Hudson says the proposal would leave the West Point historic district with "a massive scar."

According to a public notice dated Oct. 28, West Point "proposes to enter into a real estate transaction with Orange and Rockland Utilities Inc. to grant them a new easement that would alter, where necessary, an existing transmission line right-of-way on the installation and create a new 150-foot-wide transmission line right-of-way."

Public comment via the state's Coastal Consistency Review process must be submitted by 4:30 p.m. on Nov. 27 by emailing CR@dos.ny.gov and referencing Notice F-2026-0448(DA). For more details, see dub.sh/west-point-line.



Last month, the Army stopped work on its environmental impact statement for the project, citing federal changes. Earlier this year, the Trump administration approved a program that allows development on bases to forgo full environmental and historic preservation reviews, as well as state and local input, to "enable Army-wide warfighting readiness."

The Army said in February that it had considered upgrading the existing 34.5-kilovolt lines to 138kV and have them operate at 69kV with room for expansion. But it calculated that would cost $60 million more than the $113 million approved for the project, making it financially unfeasible.

Anzevino said Scenic Hudson is preparing a report with alternatives that would avoid deforestation. "Reliable power is important, but it should be achieved in the least destructive way possible," he said.